March 31, 2014

There is ongoing work at the physiotherapy

Life Award 2013

March 2014

The toilet for the store is almost completed. Tiling and plumbing works completed with toilet seat, shower, wash hand basin and urinal fixed. Door fixed – left with lock to be mounted and the exterior and entrance to the door to be plastered.

There is ongoing work at the physiotherapy where the Masons have adjusted the walls and roofing completed by the carpenters. Wall tiles for the interior of the toilet completed with floor tiles awaiting plumbers to complete laying pipes today. Work at the physiotherapy is expected to be completed by end of week.